Client: Project Management Board for Agricultural and Rural Development in Binh Dương Province
Location: Binh Nham Ward, Thuan An City
Objectives and Tasks
- Prevent floods, high tides and discharge Dau Tieng reservoir to prevent flooding of 540.98 hectares.
- Drainage with an area of 1,596 hectares.
- Water supply for production and daily life for 280 hectares
Main technical specifications
- Grade of works: grade IV
- Open-air type made of reinforced concrete, water clearing width B=(2×20)=40m
- The flat valve gate operated by a hydraulic cylinder system
- Traffic bridge with load capacity HL93, B=18m, including 04 spans
- The embankment protects both banks with SW600B prestressed reinforced concrete piles
Total investment amount/Construction cost: 284,669 billion VND
Duration:
- Commencement: 2020
- Completed: In progress.