Client:
- Hydraulic Project Investment and Construction Management Board 9
 
Location:
- Nha Be District, Ho Chi Minh City
 
Tasks of Works
- Along with other projects in the flood prevention system in Ho Chi Minh City area
 - Flood and tides control, actively regulating water level in canals, and increasing drainage capacity for urban areas, ensuring the objective of no inundating due to tides and floods.
 - Ensuring waterway traffic.
 
Main technical parameters
- Irrigation works: Grade I
 - Sluice width: Bc= (4×40) = 160m
 - Sill elevation: two middle chambers: -10.0m; two side chambers: -6.5m
 - Ship lock: Grade IV transportation works, dimension of ship lock chamber: L x B x H = 100 x 11m x 9m, bottom elevation: -5.50m
 
Total investment amount/Construction cost: 2,504,019,319,000 VND
Duration:
- Commencement in 2016
 - Completion in 2024.
 