Client:
- Irrigation Project Management Board 418 (Now Hydraulic Project Investment and Construction Management Board 10)
Location: Tieu Can district, Tra Vinh province
Tasks of Works
- The major work of the South Măng Thít irrigation project together with other projects with the following tasks:
- Saline prevention, retaining fresh water, creating fresh sources, drainage, deacidification, alkaline washing, and land reclamation for 177,792 hectares of natural land, in which 267,000 hectares for farmland. Where Cần Chông sluice directly prevents salinity, creating fresh sources for 14,040 hectares, and drainage for 16,500 hectares.
- Water supply for domestic use for people in area.
- Combine the development of waterway and road traffic and improve the ecological environment of the project area
Main technical parameters
- Grade of Works: I
- Sluice: open gate type made of reinforced concrete includes 06 chambers, B= 8x10m = 80m
- Automatic two-way valve gate made of stainless steel
- Traffic bridge load capacity HL18-X80, reinforced concrete structure M300 includes 10 girder spans, length of bridge L = 120m.
- The length of upstream canal = 922m long, the length of down stream canal 1,122m long, width of bottom B bottom = 76m.
- Homogeneous earth dam backfilling into water, length of dam L = 100m, maximum height Hmax = 12.0m
Total investment amount/Construction cost: 52,210 billion VND (2003)
Contract amount: 1,116,761,000 VND
Duration: 2000 ÷ 2002
- Commencement: 2003
- Completion: 2004