


Client:
- Hydraulic Project Investment and Construction Management Board 9
Location:
- Nha Be District, Ho Chi Minh City
Tasks of Works
- Along with other projects in the flood prevention system in Ho Chi Minh City area
- Flood and tides control, actively regulating water level in canals, and increasing drainage capacity for urban areas, ensuring the objective of no inundating due to tides and floods.
- Ensuring waterway traffic.
Main technical parameters
- Irrigation works: Grade I
- Sluice width: Bc= (4×40) = 160m
- Sill elevation: two middle chambers: -10.0m; two side chambers: -6.5m
- Ship lock: Grade IV transportation works, dimension of ship lock chamber: L x B x H = 100 x 11m x 9m, bottom elevation: -5.50m
Total investment amount/Construction cost: 2,504,019,319,000 VND
Duration:
- Commencement in 2016
- Completion in 2024.