



Client:
- Hydraulic Project Investment and Construction Management Board 5
Location:
- Huong Thuy district, Thua Thien – Hue province
Tasks of Works:
- Anti-flooding minor and early, mitigating main-season floods for the Huong river system, and limiting the flooding for Hue city. Anti-flooding early
- Supply water for domestic and industrial use with discharge Q = 2.0 m3/s.
- Create a stable irrigation water resource for 34,782 hectares of farmland in the Huong River Delta.
- Addition of freshwater resources downstream of Huong River to saline prevention, environment reclamation of mangrove area, and serving aquaculture with Q= 25.0 m3/s.
- Power generation with install capacity N = 19.5 MW
Main technical parameters
- Grade of Works: II (Standard TCXDVN 285:2002)
- Storage capacity: 646×10 6 m³
- Main dam: Rock and soil with many block; Height of dam Hmax= 60.0m; length of dam peak L = 1,187m;
- Spillway: Surface overflow spillway combined with bottom flushed gated, followed by water slope and energy dissipation by nozzle, reinforced concrete structure; Number of surface gates: 05, dimension BxH = 9.0mx10.0m; Number of gates bottom flushed 05, dimension BxH = 4.0mx3.2m
- Intake tunnel combined with construction diversion tunnel and flood discharge: Tunnel diameter D = 7.0m;
- Hydroelectric power plant:
- INumber of units: 3×6.5(MW)
- Installed capacity: 19.5 MW
Total investment amount/Construction cost: 2,000 billion VND (2005)
Contract amounut: 10,286,650,000 VND
Duration: 2005 ÷ 2016
- Commencement: November 26, 2005
- Completion: 2016